Recent and Current Construction Activity
|
|
District Project:
|
Lake Louise Road Sewer Interceptor
|
|
Status:
|
Completed January 2003
|
|
Scope:
|
Project increased the capacity to move wastewater from the District’s Sudden Valley and Geneva areas to Bellingham for treatment and disposal. Project financing method (ULID 18) resulted in voluntary 25-year development restrictions on 850 parcels.
|
|
District Project:
|
Short Sewer Extensions – Grand Blvd. and Lakewood Lane
|
|
Status:
|
Completed January 2004
|
|
Scope:
|
Constructed short sewer main extensions to serve several existing houses on septic and several proposed new houses.
|
|
District Project:
|
Sudden Valley / Geneva Water System Intertie
|
|
Status:
|
Scheduled completion February 2004
|
|
Scope:
|
Project connects Sudden Valley and Geneva water systems and increases use of the District water treatment plant in Sudden Valley. Also provides a connection for limited supply of City of Bellingham water to Sudden Valley and Geneva in emergencies.
|
|
District Project:
|
Marina Park Sewage Pump Station Replacement
|
|
Status:
|
Ready to Bid
|
|
Scope:
|
Project will replace 30-year old package pump station equipment, and facilitate portable emergency generator use to run both the Marina and Tomb Sewage Pump Stations during power outages.
|
|
District Project:
|
Ranch House Pump Station Generator Installation
|
|
Status:
|
Ready to Bid
|
|
Scope:
|
Project will improve driveway access and install a stationary emergency generator in a new building at the Ranch House Pump Station.
|
|
Developer Project:
|
Geneva Hills Subdivision
|
|
Status:
|
Under construction
|
|
Scope:
|
Seventeen-lot residential subdivision at Lakeway and Euclid, includes extensions of District water and sewer systems.
|
|
Developer Project:
|
Rivendell Subdivision
|
|
Status:
|
Completed January 2004
|
|
Scope:
|
Four-lot residential subdivision on North Shore near Agate Bay, included extension of District sewer system.
|
|
|
|